數: 7141342
源: TED
Saba Electric Company Solar Park 2
With its first Solar park becoming operational in 2018, Saba electric company NV (SEC) intends to realize a second Solar park combined with a Battery storage system on Saba to pursue its goal of having a sustainable island.
By means of a public procurement, SEC invites candidates to participate in the tender procedure for its Second solar park (with a total AC capacity of at least 1 MW) and Battery storage (of at least 1.5 MWh), combined with an Operate and maintain contract.
To receive the RfP, interested candidates must first submit to SEC a signed non-disclosure agreement (NDA).
Interested candidates can request the NDA at [email protected] The tender documentation will be available until 1.3.2017. Candidates must submit in PDF format the signed NDA on or prior to this date in order to receive the RfP.
An Engineering, Procurement, and Construction Contract for the Solar PV Plant
Saba (Bes Eilanden).
AC output capacity: at least 1 MW: SEC invites EPC contractors, within the requirements set forth in this RfP to be as creative as possible to generate as much Electricity as possible, given the available space of the site.
Perform Operations and Maintenance for the combined Phase 1 and Phase 2 Solar PV Plant
10 years of full service O&M
Implement a Battery Storage System
Battery storage system [BSS]: at least 1.5 MWh to be built at SEC’s main generator power plant.
Preferred tenderer Battery Storage System — Award intention
Preferred tenderer Solar PV Plant and Operations and Maintenance — Award Intention
The Contracting Authority announces its intention to award the contracts to the preferred bidders. Candidates (who have submitted a valid bid) are provided with the opportunity to start injunction proceedings within 20 calendar days according to the RfP. If no proceedings are initiated candidates are considered to have waived their right to contest the tender procedure or the results thereof.